Failure to comply with terms of construction contract prohibits request for change order

Plaintiff was a subcontractor on a public contract, and sought payment of $58,774 for extra work. The trial court denied Plaintiff's claim because Plaintiff had failed to obtain prior written approval, as required by the contract. On appeal, the Plaintiff attempted to rely on promises made by an engineer retained by the public authority. The appellate court rejected this claim, confirming the express language of the contract had to be followed.

The lesson to be learned is obvious. Always know and follow the language of the construction contract if asked to do additional work.

Categories: Construction Law

Stay Connected

Ehrlich, Petriello, Gudin & Plaza, Attorneys at Law - Newark Divorce Attorney

Newark

60 Park Place, Suite 1016
Newark, NJ 07102
Click for directions [+]

Morristown

89 Headquarters Plaza North, #1459
Morristown, New Jersey 07960-6834
Click for directions [+]

New York City

555 5th Avenue, 14th Floor
New York, New York 10017-3507
Click for directions [+]
View Map
Phone: (973) 862-8905 | Local Phone: (973) 643-0040.
Website:
© 2013 All rights reserved.
Attorney Web Design

The information on this website is for general information purposes only. Nothing on this site should be taken as legal advice for any individual case or situation. This information is not intended to create, and receipt or viewing does not constitute, an attorney-client relationship.